Fahrenheit construction update 3-20

After last week’s construction tour, I am back with another Fahrenheit update. The “high hat,” as they are calling it, was put in last week, and it looks great. A lot of other fun stuff is going on at the coaster as well as around the park.


There it is, all done and looking good.
You can see that work on the “loop element” has picked up. More on this later.


The parking lot is looking a lot more empty this week.


Not sure what these are for, but they were in the same lot as the track and supprots.


Those supports were not even up last week when I was there. They are for the “loop element.” The supports for the cobra roll cannot be seen from the road easily and therefore I do not have pictures of them.

You can see the rest of the pictures here. There is a lot of activity happening in the park. I saw several landscaping trucks and maintenance trucks throughout the park. Trailblazer’s trains are back on track and were test running today. Everything seems to be shaping up for the opening of the season.

Leave a Reply